Insulation of exterior walls was completed and the siding on the back wall was just about finished. Misc. trim work was begun.
The afternoon volunteer group was small so that puts more pressure on the completion date. The schedule is based on all participating churches providing four volunteers each week.
Next build day [May 20], we will continue siding, soffit and facia installation as well as trimming out the front porch. If the drywall sub finishes "mudding" and sanding the walls, [during the week] we may be able to install the interior doors.