Week 01     April 01     Assemble and errect the walls.

Week 02     April 08     Complete wall construction and install trusses. Apply roof deck if time allows.

Week 03     April 15     Easter weekend. Take the day off.

Week 04     April 22     Install roofing shingles, soffits and siding.

Week 05     April 29     Continue siding installation and porch construction.

Week 06     May 06     Continue siding & porch work.

Week 07     May 13     Continue siding and start interior painting.

Week 08     May 20     Continue  painting.

Week 09     May 27     Take the day off for Memorial day weekend.

Week 10     June 03     Landscaping by the youth and others. More painting.  [Youth landscaping day moved to June 10].

Week 11     June 10     Painting

Week 12     June 17     Cleanup and punch out.

Sunday  June 18  Dedication